As well as welding the base plate we decided to bolt it down also, the magnetic drill took it in its stride to drill trough 15mm steel with a 12mm drill once it was kept cool. 6 bolts were used
2 Nuts were welded onto the stabilizing members to allow the adjustable feet to be fixed with bolts
Next a jockey wheel was bolted to the front of the trailer
Some lugs that were damaged during galvanizing were re-made/galvanized & welded before fixing the mudguards in place
We erected the first section of mast to see how it looked & also to locate possible positions for pulley's & winches
Winch support will have to be galvanized
More soon
20/10/02